File #: 25-615    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 11/20/2025 In control: CITY COUNCIL
On agenda: 12/16/2025 Final action:
Title: Adopt a resolution approving an additional $30,000 in project contingency for the Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project CIP 25019 for a total project contingency of $88,474.58 and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Agenda

Memo to:

Manteca City Council

 

 

From:

Kevin Jorgensen II, Director of Engineering/City Engineer

 

 

Prepared by:

Toshiro Sessoms, Assistant Engineer; Donna Zapico, Assistant Engineer; Somporn Boonsalat, Deputy Director of Engineering

 

 

Date:

December 16, 2025

 

 

Subject:

Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project CIP 25019

 

Recommendation:

title    

Adopt a resolution approving an additional $30,000 in project contingency for the Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project CIP 25019 for a total project contingency of $88,474.58 and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.

 

body

Background:

On July 30, 2025, City awarded the construction contract C2025-151 to George Reed Inc. (“GRI”) for $1,516,123.10 and a project contingency of $58,474.58.

 

As of November 2025, project contingencies totaling $53,388.39 have been approved for the following work:

                     City directed change in Hot Mix Asphalt (“HMA”) aggregate size from ¾” to ½”

                     Removal of existing asphalt during construction on Wawona Street exposed native soils, which required skim patching

                     Addition of new American with Disabilities Act (“ADA”) curb ramp on Wawona Street & Willow Avenue

                     Additional utility adjustments and increased paving area

                     Installation of City furnished speed lumps on Locust Avenue

 

Only $5,086.19 in project contingencies remain.

 

To maximize the project improvements, staff is requesting an additional $30,000 in project contingency for the following work:

                     To change the Locust Avenue improvement from a rubber cape seal to a 2-inch grind and overlay

                     Updating of eight new ADA curb ramps on Locust Avenue to current standards

                     Contractor has provided a quote of $25,731.55 to complete this work

 

The $30,000.00 in project contingency will be funded by construction management cost savings.

 

Fiscal Impact:

 

There is sufficient funding available in the FY2025-26 Capital Improvement Program project budget in CIP No. 25019 for this recommendation in Fund 425 Gas Tax/Street Improvements SB1 and Fund 440 Measure K.

 

The Project funding summaries are as follows:

Funding Type

Amount

ATP Cycle 7

   $800,000.00

MKR SRTS

   $358,585.72

SB1 (2024 PMP CIP No. 24110 savings)

   $566,011.96

Total

$1,724,597.68

 

The Project Expenses are as follows:

Description

Original Amount

Amendment

Request Increase/ Decrease

Total

Construction Management (Ghirardelli Associates)

   $100,000.00

$50,000.00

   ($30,000)

   $120,000.00

Construction Contract (GRI)

$1,516,123.10

-

-

$1,516,123.10

Project Contingency

     $58,474.58

-

     $30,000

     $88,474.58

Total =

$1,674,597.68

$50,000.00

-

$1,724,597.68

 

 

 

Documents Attached:

1.                     Attachment 1 - Resolution

2.                     Attachment 2 - Location Map