Manteca CA banner
File #: 24-402    Version: 1 Name:
Type: Discussion Items Status: Agenda Ready
File created: 7/31/2024 In control: CITY COUNCIL
On agenda: 10/1/2024 Final action:
Title: Receive an update on Pavement Maintenance Program and project estimates and provide direction regarding Council priorities.
Attachments: 1. Attachment 1 - Presentation File, 2. Attachment 2 - PMP Cost Map, 3. Attachment 3 - PMP Priority Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Agenda

Memo to:

Manteca City Council

 

 

From:

Kevin Jorgensen II, Director of Engineering/City Engineer

 

 

Prepared by:

Alfredo Mijango, Associate Engineer; Somporn Boonsalat, Deputy Director of Engineering

 

 

Date:

October 1, 2024

 

 

Subject:

Pavement Maintenance Program Update

 

Recommendation:

title    

Receive an update on Pavement Maintenance Program and project estimates and provide direction regarding Council priorities.

 

body

Background:

At the February 21, 2023, City Council meeting, staff shared the results of the 2023 Pavement Condition Index. Council articulated the importance of having both a preventative and corrective Pavement Maintenance Program.  Staff was directed to develop a list of pavement improvement projects and report back for City Council feedback and direction.

 

At the City Council meeting April 18, 2023, Council provided direction to staff to prioritize funding for the arterial/collector road improvement projects as shown below. The table has been updated to reflect current project status.

 

 

Council Priority Projects - Major Roadways

Status

Cost Estimate

1

Louise Avenue (Main Street to Highway 99)

In Construction

$2,240,818

2

Lathrop Road (Union Road to Highway 99)

In Construction

$1,874,525

3

Center Street (west of Union Road) - Project by Public Works

Completed

 

4

Airport Way widening (Wawona Street to Drain 5)

Utility Coordination

TBD

5

Spreckels Avenue (Moffat Boulevard to Yosemite Avenue) Project by Public Works

Partially Completed

 

6

Wawona Street (Union Road to Locust Avenue)

Pending funding availability

   $800,000

7

Mission Ridge Drive (Tahoe Street to Vanderbilt Court)

Pending funding availability

   $600,000

8

Woodward Avenue (Main Street to Pillsbury Road)

Pending funding availability

$5,500,000

9

Yosemite Avenue (Airport Way west to Rail Road tracks)

Pending funding availability

$4,500,000

 

 

 

Recommended Priority Projects - Residential Streets (Local)

Status

Cost Estimate

A

Shasta Park area, boundary Main Street, Louise Avenue, Edison Street and Highway 99

Pending funding availability

$8,000,000

B

Cotta Park area, boundary Union Road, Wawona Street, Main Street, and Highway 120

Pending funding availability

$7,000,000

C

Union West Park area, boundary Grand Prix Avenue, Mercedes Avenue, Wawona Street, Union Road, and Yosemite Avenue

Pending funding availability

$2,500,000

 

 

Fiscal Impact:

 

There is no general fund impact.

Documents Attached:

1.                     Attachment 1 - Presentation File

2.                     Attachment 2 - PMP Cost Map

3.                     Attachment 3 - PMP Priority Map