City Council Agenda
Memo to: |
Manteca City Council |
|
|
From: |
Kevin Jorgensen II, Director of Engineering/City Engineer |
|
|
Prepared by: |
Kyzen Nicolas, Associate Engineer; Somporn Boonsalat, Deputy Director of Engineering |
|
|
Date: |
October 21, 2025 |
|
|
Subject: |
Main Street (Northgate Drive to Alameda Street) Bike & Pedestrian Improvement Project CIP No. 20005 |
Recommendation:
title
Adopt a resolution approving an additional $96,125.51 in project contingency for the Main Street (Northgate Drive to Alameda Street) Bike & Pedestrian Improvement Project CIP 20005 and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
On December 17, 2024, City awarded the construction contract C2025-05 to United Pavement Maintenance, Inc. (“UPM”) for $2,995,249.25 and approved a project contingency of $300,000.
As of September 2025, the following contingencies totaling $246,910.12 have been approved:
• $206,910.12 in Field Directives for
o Americans with Disabilities Act compliant curb ramps at the Main Street intersections with Alameda Street, Northgate Drive, and Jason Street
o Tree removal and concrete curb, gutter, and sidewalk repair near Edison Street & Main Street intersection
o Concrete median modification at the northbound Main Street left turn lane into Parkwest Casino driveway and at the southbound Main Street left turn lane into Cardoza Center driveway
o Pedestrian fence footing connection change to base plate
o Replacement of faulty electrical conductors and cables at Alameda Street & Main Street intersection
o Additional Iteris traffic signal video detection extension modules
o Additional pavement rehabilitation at the Alameda Street & Main Street intersection
• $40,000 for TRC Engineers, Inc. for additional Construction Management and Inspection Services
During the installation of the new concrete median, a layer of concrete was discovered below the existing asphalt pavement. This information was not known during design and was not discovered as part of the project site investigations. The design consultant, Mark Thomas, recommended the addition of geosynthetic fabric to mitigate against future reflective cracking.
UPM provided City staff with a cost estimate of approximately $340,428.00 for the placement of the geosynthetic fabric across the full road width. City worked with Mark Thomas and UPM to secure pricing from multiple geosynthetic fabric manufacturers and was able to arrive at a negotiated installation cost of $127,660.50.
Staff is requesting City Council to approve an additional $96,125.51 in project contingency to maximize the Project improvements.
Fiscal Impact:
There is sufficient funding available in the FY2025-26 Capital Improvement Program project budget in CIP No. 20005 for this recommendation.
The Project funding summaries are as follows:
Funding Type |
Amount |
Federal HSIP Grant - Design |
$273,600 |
SB 1 - Design |
$24,383 |
Fund 460 Local Transportation Fund - Original City Match |
$214,960 |
Federal HSIP Grant - Original Construction |
$1,661,040 |
Federal HSIP Grant - Additional Construction |
$850,000 |
Measure K Regional ATP Grant - Construction |
$1,000,000 |
Fund 460 Local Transportation Fund - Construction |
$1,018,177 |
Total |
$5,042,160 |
The Project Expenses are as follows:
Description |
Original Amount |
Approved Changes |
Requested Increase |
Total |
Design (Mark Thomas) |
$303,818.02 |
$24,382.45 |
- |
$328,200.47 |
Construction (UPM) |
$2,995,249.25 |
$1,066,287.65 |
- |
$4,061,536.90 |
Construction Management (TRC) |
$184,000.00 |
$72,297.12 |
- |
$256,297.12 |
Project Contingency |
$300,000 |
- |
$96,125.51 |
$396,125.51 |
Total |
$3,783,067.27 |
$1,162,967.22 |
$96,125.51 |
$5,042,160 |
Documents Attached:
1. Attachment 1 - Resolution
2. Attachment 2 - Location Map