City Council Agenda
|
Memo to: |
Manteca City Council |
|
|
|
|
From: |
Toni Lundgren, City Manager |
|
|
|
|
Prepared by: |
Vielka Guarascio, Homeless and Housing Services Manager |
|
|
|
|
Date: |
December 1, 2026 |
|
|
|
|
Subject: |
Professional Services Agreement with WMB Architects for Architectural and Engineering Services for the Navigation Center & Affordable Housing Project (CIP 24001) |
Recommendation:
title
Adopt a resolution approving a Professional Services Agreement with WMB Architects in the amount of $1,073,000 for Architectural and Engineering (A&E) Services for the Navigation Center & Affordable Housing project (CIP 24001) and approve a contingency of $107,300 (10%), for a total of $1,180,300; and authorizing the City Manager or designee to execute agreement and all associated documents.
body
Background:
The City proposes to convert the former Qualex Building at 555 Industrial Park Drive into a permanent, low-barrier Navigation Center offering 24-hour shelter and coordinated services for people experiencing homelessness. The facility will support intake, sleeping accommodations, hygiene, meals, case management and housing navigation. The City plans to select the shelter operator through a separate procurement.
The City released the Request for Proposals (RFP) on September 28, 2026, and held a mandatory site walk on October 15, 2026. The City issued written clarifications to help firms prepare proposals. By the November 3, 2026 deadline, the City received 13 timely proposals. The selection committee evaluated the technical proposals and shortlisted four firms for interviews.
On November 17, 2026, the selection committee interviewed the four shortlisted firms to assess their qualifications, experience with similar renovations, proposed team and approach to delivering the project. Fee proposals were submitted separately from technical proposals. Under the RFP, the City reviews and negotiates the fee after identifying the most qualified firm.
The selection committee ranked WMB Architects as the most qualified firm based on their experience with similar projects, local presence, understanding of the project’s needs, and ability to adapt its approach as the design progresses. Based on the committee’s evaluation and the negotiated scope of services and fee, staff recommends awarding the contract to WMB Architects.
Under the agreement, the A&E team will validate the City’s operating program during conceptual design, verify existing building and site conditions, and review the City’s roof, structural repair, and remediation records. Based on that work, the consultant will identify the building and site improvements needed to support the proposed use and advance the City-approved design through permitting. The consultant will prepare a complete, coordinated, bid-ready package, including signed and stamped construction drawings, technical specifications, and a final construction cost estimate. The consultant will also support the City during bidding, provide construction administration services, and assist with project closeout.
The City is coordinating federal environmental review under the National Environmental Policy Act (NEPA) because the project receives federal funding. The City will coordinate California Environmental Quality Act (CEQA) review through its environmental consultant in parallel with design. The A&E team will provide plans and other design information to support those reviews. This action approves professional services, and construction award will be addressed separately.
Fiscal Impact:
Sufficient budget is available in the Fiscal Year 2026-27 budget in the Navigation Center Fund (Fund 126), Navigation Center & Affordable Housing project (CIP 24001), to cover this agreement.
There is no General Fund impact.