City Council Agenda
Memo to:
Manteca City Council
From:
Mike Selling, Assistant Director of Engineering/City Engineer
Prepared by:
Wing Chang, Assistant Engineer;
Somporn Boonsalat, Deputy Director of Engineering
Date:
May 12, 2026
Subject:
Construction Management & Inspection Services for Yosemite Ave (Walnut Ave to Main Street) Bike & Pedestrian Improvement Project CIP No. 20006
Recommendation:
title
Adopt a resolution approving an agreement with Albat for construction management and inspection services for the Yosemite Ave (Walnut Ave to Main Street) Bike & Pedestrian Improvement Project CIP No. 20006 in an amount not-to-exceed $287,204.91; and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
The Highway Safety Improvement Program (HSIP) is a federal grant program administered by Caltrans on behalf of the Federal Highway Administration that funds transportation-related safety projects. The Yosemite Ave (Walnut Ave to Main Street) Bike & Pedestrian Improvement Project CIP No. 20006 (Project), partially funded by HSIP, includes the installation of:
* New 12-inch Water Main
* New bike lanes
* Updated ADA and curb ramps to current standards
* New rectangular rapid flashing beacon system
* New signage and stripping
* Pavement rehabilitation by grinding and installing 3-inches of asphalt pavement
On April 7, 2026, the City awarded the construction contract for the Project to United Pavement Maintenance, Incorporated.
Leading up to the award of this contract the City was concurrently engaged seeking Construction Management & Inspection Services (CM&IS) for the Project.
On March 12, 2026, the City issued a Request for Proposals for CM&IS for the Project.
On April 2, 2026, the following proposals for CM&IS were received:
* Albat
* 4Leaf
* Interwest
The City formed an evaluation committee to review and rank all proposals based on the adv...
Click here for full text