City Council Agenda
|
Memo to: |
Manteca City Council |
|
|
|
|
From: |
Carl Brown, Public Works Director |
|
|
|
|
Prepared by: |
Michael Rosales, Park Planning and Development Manager |
|
|
|
|
Date: |
June 3, 2025 |
|
|
|
|
Subject: |
Accept All Improvements from the Manteca Golf Course Crom Street Fencing Project (CIP 24037) |
Recommendation:
title
Adopt a resolution accepting all improvements for the Manteca Golf Course Crom Street Fencing Project (CIP 24037) as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to complete and execute all associated documents, and take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
On December 3, 2024, City Council awarded the construction contract C2024-198 for the Manteca Golf Course Crom Street Fencing Project (CIP 24037) to Westside Landscape and Concrete, Inc. for (Contractor) for an amount of $248,190.46 and approved a construction contingency of $31,809.54 for a total project budget of $280,000.
The Project was constructed in general conformance with the conformed plans and specifications.
The final Project had no change orders.
The final project construction cost is $248,190.46, the Contractor has submitted the signed final payment certification (Attachment 3)
The total retention of $12,409.52 will be released to the Contractor no sooner than 45 days after filing completion.
Fiscal Impact:
There is no fiscal impact associated with this action.
Documents Attached:
1. Attachment 1 - Resolution
2. Attachment 2 - Notice of Completion
3. Attachment 3 - Payment Certification
4. Attachment 4 - Vicinity and Location Map