City Council Agenda
Memo to:
Manteca City Council
From:
Kevin Jorgensen II, Director of Engineering/City Engineer
Prepared by:
Toshi Sessoms, Assistant Engineer; Donna Zapico, Assistant Engineer
Date:
June 17, 2025
Subject:
Shasta Park Area Pavement Improvement Project (bounded by N. Main Street, E. Louise Avenue, Hwy 99, and E. Edison Street)
Recommendation:
title
Adopt a resolution amending the Fiscal Year 2024-25 Capital Improvement Program to include the Shasta Park Area Pavement Improvement Project and assign a Capital Improvement Project Number; approving the Plans and Specifications for the Shasta Park Area Pavement Improvement Project (bounded by N. Main Street, E. Louise Avenue, Hwy 99, and E. Edison Street); approving the California Environmental Quality Act Notice of Exemption determination (exempt from CEQA pursuant to 14 Cal. Code Regs. ? 15301(c); authorizing a Call for Bids; and authorizing the City Manager or Designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
The City Council has stressed the importance of pavement maintenance to prolong existing pavement life and reduce more costly repairs in the future.
In order to expedite the construction schedule and optimize use of local funds, staff has prepared the Plans, Specifications, and Estimate (PS&E) for the Shasta Park Area Pavement Improvement Project (the "Project"). The Project includes placement of rubberized cape seal, asphalt overlay, installation of ADA curb ramps, digout repairs, crack sealing, and striping.
The Project is located in the Shasta Park area, east of N. Main Street, south of E. Louise Avenue, west of Hwy 99, and north of E. Edison Street, see Attachment 4 - Location Map.
The Engineer's estimate for the Project construction is $1,700,000, and does not include any additional design services, funding requirements, construction management, or Project contingencies.
Staff has reviewe...