Subject:
Yosemite Avenue Pavement Improvement Project STPL-5242(042)
Recommendation:
title
Adopt a resolution approving Plans and Specifications for the Yosemite Avenue Pavement Improvement Project STPL-5242(042) (District 3: Walnut Ave to West City Limit); amending the Fiscal Year 2025-2026 Capital Improvement Program (CIP) to include the Yosemite Avenue Pavement Improvement Project STPL-5242(042) (Project) and assign a CIP Number; approving the California Environmental Quality Act Notice of Exemption determination for the Project; authorizing a Call for Bids; and authorizing the City Manager or designee to award the Project construction contract up to $5,762,744 inclusive of a 10% contingency and take all appropriate actions necessary to carry out the purpose and intent of the resolution. (Exempt from CEQA pursuant to 14 Cal. Code Regs. ? 15301(c).).
body
Background:
On October 21, 2025, the City of Manteca City Council prioritized Yosemite Ave (Airport Way to Westerly Railroad tracks) and Yosemite Ave (Airport Way to Union Rd) as priorities 1 and 2, respectively, for future pavement improvement projects.
Staff worked with the San Joaquin Council of Governments to identify $5,762,744 in Federal Surface Transportation Block Grant (STBG) for pavement improvement along Yosemite Avenue.
To expedite the construction schedule and optimize use of funds, staff has prepared the Project Plans, Specifications, and Estimate (PS&E). The Project includes removal and replacement of existing asphalt, and new striping within Yosemite Avenue from Walnut Ave to the West City Limit.
The Engineer's Estimate for the Project is $4,500,000 plus a 10% construction contingency estimated at $450,000 for a total estimated cost of $4,95...