City Council Agenda
Memo to:
Manteca City Council
From:
Kevin Jorgensen II, Director of Engineering/City Engineer
Prepared by:
Kyzen Nicolas, Associate Engineer;
Somporn Boonsalat, Deputy Director of Engineering
Date:
October 21, 2025
Subject:
Main Street (Northgate Drive to Alameda Street) Bike & Pedestrian Improvement Project CIP No. 20005
Recommendation:
title
Adopt a resolution approving an additional $96,125.51 in project contingency for the Main Street (Northgate Drive to Alameda Street) Bike & Pedestrian Improvement Project CIP 20005 and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
On December 17, 2024, City awarded the construction contract C2025-05 to United Pavement Maintenance, Inc. ("UPM") for $2,995,249.25 and approved a project contingency of $300,000.
As of September 2025, the following contingencies totaling $246,910.12 have been approved:
* $206,910.12 in Field Directives for
o Americans with Disabilities Act compliant curb ramps at the Main Street intersections with Alameda Street, Northgate Drive, and Jason Street
o Tree removal and concrete curb, gutter, and sidewalk repair near Edison Street & Main Street intersection
o Concrete median modification at the northbound Main Street left turn lane into Parkwest Casino driveway and at the southbound Main Street left turn lane into Cardoza Center driveway
o Pedestrian fence footing connection change to base plate
o Replacement of faulty electrical conductors and cables at Alameda Street & Main Street intersection
o Additional Iteris traffic signal video detection extension modules
o Additional pavement rehabilitation at the Alameda Street & Main Street intersection
* $40,000 for TRC Engineers, Inc. for additional Construction Management and Inspection Services
During the installation of the new concrete median, a layer of concrete was discovered below the existing asphalt...