Approve a budget appropriation for the Woodward Park Splash Pad Project - CIP 24086 |
Recommendation:
title
Adopt a resolution approving a budget appropriation of $400,000 in the Park Acquisition and Improvement Fund (Fund 500) for the Woodward Park Splash Pad Project (CIP 24086); and authorize the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
The improvements in the Woodward Park Splash Pad Project (CIP 24086) include relocating the existing restroom structure in Phase II of the project to serve the community better and accommodate increased usage during events and high-traffic periods. A recent evaluation of the existing restroom facility structure has revealed that the structure has significant structural and cosmetic issues and cannot be relocated safely. Staff recommends replacing the structure after weighing the estimated costs of repairing the damage and vandalism the structure has experienced over the two decades it has been in service.
Staff requests an appropriation of $400,000 to demolish the existing structure and purchase a new restroom utilizing a cooperative purchase agreement.
Fiscal Impact:
A supplemental appropriation of $400,000 will be processed in the Park Acquisition and Improvement Fund (Fund 500) and allocated to the Woodward Park Splash Pad Project (CIP 24086). The FY26 amended budget for CIP 24086 will increase to $4,174,014.
Documents Attached:
1. Attachment 1 - Resolution