City Council Agenda
Memo to: Manteca City Council
From: George Montross, Director of Utilities
Date: December 1, 2026
Subject: Notice of Completion – WQCF Breakroom and Operator Control Room Remodel Project CIP No. 24047
title
Adopt a resolution accepting all improvements for the WQCF Breakroom and Operator Control Room Remodel Project CIP No. 24047 as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
On October 21, 2025, the City awarded construction contract C2025-191 to Diede Construction, Inc. for $1,909,000 with a ten percent (10%) contingency of $190,900.
The project involves the remodel of an existing building, which was constructed in 1972, into a training room, staff breakroom and an operator control room. During construction activities there were multiple discoveries of unknown items, which were not included in the original construction drawings and needed to be corrected through the change order process.
On June 2, 2026, the City Council approved an additional contingency of $250,000 to cover communication, network, audio/visual improvements as well as additional unforeseen project improvements.
The Project included a total of four contract change orders, adding a total of $390,169.69 to the original contract amount. The change order work included the following:
Abatement of asbestos material.
Addition of ADA path of travel and access improvements.
Roof, window and interior wall modifications.
Network / fiber optic communication improvements.
The final construction cost is $2,299,169.69 and the Contractor has signed the final payment certification (Attachment 3).
There is a 5% retention totaling $114,958.69 that will be released to the Contractor no sooner than 45 days after filing the Notice of Completion at the San Joaquin County Recorder’s Office.
F...
Click here for full text