Legislation Details

File #: 26-366    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 7/1/2026 In control: CITY COUNCIL
On agenda: 10/20/2026 Final action:
Title: Adopt a resolution approving the final balancing construction contract change order No. 3 with George Reed Inc. in the amount of $99,978.85 for the Safe Routes to School Project CIP 23006; accepting all improvements for Safe Routes to School Project CIP No. 23006 as complete; authorizing the City Clerk to file the Notice of Completion; and authorizing the City Manager or their designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Final Balancing Construction Contract Change Order No. 3, 3. Attachment 3 – Notice of Completion, 4. Attachment 4 – Final Payment Certification, 5. Attachment 5 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Agenda
Memo to:
Manteca City Council




From:
Michael Selling, Director of Engineering/City Engineer
Prepared by: Beshoy Demyan Senior Enginner; Somporn Boonsalat, Deputy Director of Engineering Date:
October 20, 2026 Subject:
CIP 23006 Safe Routes to School – Notice of Completion and Balancing Contract Change Order No. 3
Recommendation:
title
Adopt a resolution approving the final balancing construction contract change order No. 3 with George Reed Inc. in the amount of $99,978.85 for the Safe Routes to School Project CIP 23006; accepting all improvements for Safe Routes to School Project CIP No. 23006 as complete; authorizing the City Clerk to file the Notice of Completion; and authorizing the City Manager or their designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.

body
Background:
The Safe Routes to School Project CIP 23006 (“Project”) is focused on improvements in the areas surrounding Manteca High School, Sierra High School, Golden West Elementary School, Shasta Elementary School, Stella Brockman Elementary School, and Brock Elliott Elementary School. The project includes the installation of enhanced pedestrian crossings, ADA-compliant curb ramps and sidewalks, a new pedestrian hybrid beacon, and a traffic signal. These improvements aim to enhance pedestrian access and ensure safer travel for students attending the six schools in Manteca.

In 2022, the City of Manteca (“City”) was awarded $1.5 million in funding from the Measure K, Safe Route to School Program from the San Joaquin Council of Governments (“SJCOG”) for the Safe Routes to School Project (CIP 23006).

On February 27, 2025, the City was awarded $3,814,045 in Regional Alternative Transportation Program (ATP) Cycle 7 Measure K grant funding (“ATP Cycle 7”) by SJCOG. Staff recommended allocating $1,800,000 of the ATP Cycle 7 funds to the Main Street (CIP 20005 / $1,000,000) and Wawona Bike and Pedes...

Click here for full text