Legislation Details

File #: 26-407    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 7/31/2026 In control: CITY COUNCIL
On agenda: 8/18/2026 Final action:
Title: Adopt a resolution accepting all improvements for the Woodward Park Splash Pad and Improvements Project (CIP 24086) as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to complete and execute all associated documents, and take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Notice Of Completion - Suarez and Munoz Construction Inc, 3. Attachment 3 - Change Order 1, 4. Attachment 4 - Final Payment Certification-Suarez and Munoz Construction, 5. Attachment 5 - Vicinity and Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

City Council Agenda

Memo to:

Manteca City Council

 

 

From:

Michael Rosales, Park Planning and Development Manager

 

 

Date:

August 18, 2026

 

 

Subject:

Woodward Park Splash Pad and Improvements Project (CIP 24086)

 

Recommendation:

title    

Adopt a resolution accepting all improvements for the Woodward Park Splash Pad and Improvements Project (CIP 24086) as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to complete and execute all associated documents, and take all appropriate actions necessary to carry out the purpose and intent of the resolution.

body

Background:

On April 15, 2025, City Council awarded the construction contract C2025-196 for the Woodward Park Splash Pad and Improvements (CIP 24086) including Additive Alternate No. 1, 2 and 3 to Suarez & Munoz Construction, Inc. in the amount of $2,798,000 and approving a project construction contingency not-to exceed $209,850 (7.5%), for a total construction budget of $3,007,850.

 

The Project had one change order. Change Order Number 1 was in the amount of  $157,916.45 which included a total of 10 preliminary change orders (Attachment 3)

 

The Project was constructed in general conformance with the conformed plans and specifications. 

 

The final project construction cost is $2,950,916.45; the Contractor has submitted the signed final payment certification (Attachment 4).

 

The total retention of $147,545.84 will be released to the Contractor no sooner than 45 days after filing the notice of completion (Attachment 2).

 

Fiscal Impact:

There is no fiscal impact with this action.

 

 

Documents Attached:

1.                     Attachment 1 - Resolution

2.                     Attachment 2 - Notice of Completion

3.                     Attachment 3 - Change Order No. 1

4.                     Attachment 4 - Payment Certification

5.                     Attachment 5 - Vicinity and Location Map