Skip to main content
Manteca CA banner
File #: 25-306    Version: 1 Name:
Type: Public Hearings Status: Agenda Ready
File created: 5/28/2025 In control: CITY COUNCIL
On agenda: 6/17/2025 Final action:
Title: Conduct a Public Hearing for the S. Main Street Widening and Improvements Area of Benefit formation and adopt a resolution approving the Engineer's Report for the S. Main Street Widening and Improvements Area of Benefit, forming the S. Main Street Widening and Improvements Area of Benefit District; approving the Improvement Agreement for the Marketplace @ Main (Offsite) Improvements; approving the use of Development Agreement fees in the amount of $1,017,691.00 and a contingency not-to-exceed $101,769.10 (10%), for a total amount of $1,119,460.10 to fund the unfunded portion of the Marketplace @ Main (Offsite) Improvements; authorizing the City Manager or designee to execute all associated documents and take all appropriate actions necessary to carry out the purpose and intent of this resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - The S. Main Street Widening and Improvements Area of Benefit Engineer’s Report, 3. Attachment 3 - Marketplace @ Main (Offsite) Improvement Agreement, 4. Attachment 4 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Agenda
Memo to:
Manteca City Council


From:
Kevin Jorgensen II, Director of Engineering/City Engineer


Prepared by:
Lauren Silva, Associate Engineer


Date:
June 17, 2025


Subject:
S. Main Street Widening and Improvements Project - Area of Benefit, Improvement Agreement and City Funding Contribution

Recommendation:
title
Conduct a Public Hearing for the S. Main Street Widening and Improvements Area of Benefit formation and adopt a resolution approving the Engineer's Report for the S. Main Street Widening and Improvements Area of Benefit, forming the S. Main Street Widening and Improvements Area of Benefit District; approving the Improvement Agreement for the Marketplace @ Main (Offsite) Improvements; approving the use of Development Agreement fees in the amount of $1,017,691.00 and a contingency not-to-exceed $101,769.10 (10%), for a total amount of $1,119,460.10 to fund the unfunded portion of the Marketplace @ Main (Offsite) Improvements; authorizing the City Manager or designee to execute all associated documents and take all appropriate actions necessary to carry out the purpose and intent of this resolution.

body
Background:
In accordance with the City's adopted Transportation Public Facilities Implementation Plan (P.F.I.P.) the S. Main Street corridor between State Highway 120 (SR120) and Woodward Avenue will ultimately be a 6-lane multimodal road with a median. Currently, this corridor is primarily a two-lane roadway with no sidewalk, curb or gutter.

Roadways are normally widened and improved as projects develop on the parcels that front the roadway. Because the properties adjacent to the 2-lane portion of the S. Main Street corridor are undeveloped, there is a "bottle neck" in the roadway system. The unimproved 2-lane portion of the corridor is bounded by the following properties.
- 1437 and 1533 S. Main Street on the west side, north of Atherton Drive (Aretakis),
- 1601 and 1669 S. Main Street on the west side, south of Ath...

Click here for full text