File #: 25-274    Version: 1 Name:
Type: Discussion Items Status: Agenda Ready
File created: 5/13/2025 In control: CITY COUNCIL
On agenda: 10/21/2025 Final action:
Title: Receive an annual update on the Pavement Maintenance Program and provide direction regarding Council priorities.
Attachments: 1. Attachement 1 - PowerPoint
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Agenda
Memo to:
Manteca City Council


From:
Kevin Jorgensen II, Director of Engineering/City Engineer


Prepared by:
Alfredo Mijango, PE, Associate Engineer;
Somporn Boonsalat, Deputy Director of Engineering


Date:
October 21, 2025


Subject:
Pavement Maintenance Program 2025 Update

Recommendation:
title
Receive an annual update on the Pavement Maintenance Program and provide direction regarding Council priorities.

body
Background:
In February 2023, staff shared the results of the 2023 Pavement Condition Index Study. Council articulated the importance of having both a preventative and corrective Pavement Maintenance Program. Staff was directed to develop a list of pavement improvement projects and report back for City Council feedback and direction.

On October 1, 2024, Council provided direction to staff to prioritize funding for certain roadway sections based on Council's priority projects. Since then, multiple roadway priority projects have been completed by either the Public Works or Engineering Department. For clarity, and ease of discussion completed project(s) have been removed and separate tables have been created to segregate the active and future projects which need to be prioritized.

Active Projects by Engineering
Status
Airport Way Widening (Wawona St to Drain 5) - Rule 20A
Pre-Design
Shasta Park Area (Garden Gate Dr, Louise Ave, Highway 99, and Edison St)
2025 Construction
Wawona St (Union Rd to Main St)
2025 Construction
Locust Ave (Wawona St to Mission Ridge Dr)
2025 Construction
Edison St / Garden Gate Dr (Shasta Area)
2025 Construction
Yosemite Ave (Union Rd to Willow Ave) - HSIP bike & ped
Design for 2026 Const.




Active Projects by Public Works
Description
Spreckels Ave (Norman Dr to Yosemite Ave) FY26
Minor repairs within area
Louise Ave (Airport Way to Main St) FY26 - FY28
Minor repairs within area
Industrial Park Dr (Main St to Moffat Blvd) FY26 - FY28
Minor repairs within area

Recommendation
Future - Major Ro...