Skip to main content
Manteca CA banner
File #: 26-103    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 2/11/2026 In control: CITY COUNCIL
On agenda: 3/3/2026 Final action:
Title: Adopt a resolution approving two budget appropriations of $48,766 from the Highway Interchange Fund (Fund 240) and $806 from the Traffic Signal Fund (Fund 220) to the Safe Route to Schools Project (CIP# 23006); and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Project Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Agenda
Memo to:
Manteca City Council


From:
Michael Selling, Assistant Director of Engineering / City Engineer


Prepared by:
Beshoy Demyan Senior Enginner; Somporn Boonsalat, Deputy Director of Engineering


Date:
March 3, 2026


Subject:
CIP 23006 Safe Routes to School Project - Budget Appropriation

Recommendation:
title
Adopt a resolution approving two budget appropriations of $48,766 from the Highway Interchange Fund (Fund 240) and $806 from the Traffic Signal Fund (Fund 220) to the Safe Route to Schools Project (CIP# 23006); and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.

body
Background:
The CIP 23006 Safe Routes to School Project ("Project") is focused on improvements in the areas surrounding Manteca High School, Sierra High School, Golden West Elementary School, Shasta Elementary School, Stella Brockman Elementary School, and Brock Elliott Elementary School. The project includes the installation of enhanced pedestrian crossings, ADA-compliant curb ramps and sidewalks, a new pedestrian hybrid beacon, and a traffic signal. These improvements aim to enhance pedestrian access and ensure safer travel for students attending these schools.

The Project's total costs, including design, construction, construction management, and contingency total $4,463,617, which is broken down on the following table:


Description
Original Amount
Amendment/
Contract Change
Estimate
Total
Design
$260,630
$39,370

$300,000
Construction
$3,654,700


$3,654,700
Project Contingency


$106,108
$106,108
Construction Management
$402,809


$402,809
Total
$4,318,139
$39,370
$106,108
$4,463,617




On July 30, 2025, the City Council awarded the Project's construction contract to George Reed, Inc. in the amount of $3,654,700.

Recently during the Project construction, additional pavement work necessary to meet ADA requirements at 10 of the curb ramps to be replaced under t...