Skip to main content
Manteca CA banner
File #: 25-424    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 8/13/2025 In control: CITY COUNCIL
On agenda: 9/16/2025 Final action:
Title: Adopt a resolution accepting all improvements for the Nile Garden Well 30 Water Supply Project - Well Drilling (CIP 21026 & 21034) as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to complete and execute all associated documents and take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Location Map, 3. Attachment 3 - Notice of Completion, 4. Attachment 4 - Final Payment Certification
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Agenda
Memo to:
Manteca City Council


From:
Kevin Jorgensen II, Director of Engineering/City Engineer


Prepared by:
Elba Mijango, Associate Engineer;
Somporn Boonsalat, Deputy Director of Engineering


Date:
September 16, 2025


Subject:
Notice of Completion - Drilling of Well 30 at Palmer Park, Nile Garden Well 30 Water Supply Project CIP 21034 and 21026

Recommendation:
title
Adopt a resolution accepting all improvements for the Nile Garden Well 30 Water Supply Project - Well Drilling (CIP 21026 & 21034) as complete, authorizing the City Clerk to file the Notice of Completion, and authorizing the City Manager or designee to complete and execute all associated documents and take all appropriate actions necessary to carry out the purpose and intent of the resolution.

body
Background:
On June 20, 2023, City Council awarded the construction contract to Nor-Cal Pump & Well Drilling (Nor-Cal) in the amount of $927,853 and approved a construction contingency of 15% or $139,178 for a total not-to-exceed project cost of $1,067,031 for the Nile Garden Well 30 Water Supply Project - Well Drilling (CIP 21026 & 21034) ("Project").

The Project was constructed in general conformance with the conformed plans and specifications.

The project included three contract change orders having a total project cost reduction of $19,900.

A summary of the change orders is as follows:

* Temporary pause in construction to allow for a geotechnical investigation.
* Installation of a larger casing pipe.
* Project credit for quantity adjustments of irrigation materials, and reduction to steel casing length.

The final construction cost is $907,953 and the Contractor has signed the final payment certification, see Attachment 4.

There is a 5% retention totaling $45,397.65 that will be released to the Contractor no sooner than 45 days after filing of the Notice of Completion with the San Joaquin County Clerk.

Fiscal Impact:
There is no fiscal impact associated with ...