Skip to main content
Manteca CA banner
File #: 25-130    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 3/10/2025 In control: CITY COUNCIL
On agenda: 6/17/2025 Final action:
Title: Approve Traffic Calming Measures along Wawona Street (from Airport Way to Junction Drive) and along Elm Avenue (from W. Alameda Street to Blossom Drive); and direct staff to take all appropriate actions necessary to implement improvements in accordance with the Manteca Traffic Calming Program.
Attachments: 1. Attachment 1 – Wawona Street and Elm Avenue Traffic Calming Plans, 2. Attachment 2 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Agenda
Memo to:
Manteca City Council


From:
Kevin Jorgensen II, Director of Engineering/City Engineer


Prepared by:
Beshoy R Demyan, Senior Engineer;
Somporn Boonsalat, Deputy Director of Engineering


Date:
June 17, 2025


Subject:
Traffic Calming Measures along Wawona Street and Elm Avenue

Recommendation:
title
Approve Traffic Calming Measures along Wawona Street (from Airport Way to Junction Drive) and along Elm Avenue (from W. Alameda Street to Blossom Drive); and direct staff to take all appropriate actions necessary to implement improvements in accordance with the Manteca Traffic Calming Program.

body
Background:
On November 20, 2018, the City Council adopted the Manteca Traffic Calming Program (MTCP). The MTCP established a detailed ten-step process for the City and residents to follow when working to address traffic concerns related to speeding.

The communities along the subject segments of Wawona Street and Elm Avenue requested traffic calming measures (Step 1) and City staff responded by following the step-by-step Traffic Calming Process per the MTCP. The steps taken are listed below (Steps 9 and 10 will be completed pending City Council approval):

? Step 1: Project Initiation: Report the Problem
? Step 2: Community Survey
? Step 3: Data Collection
? Step 4: Stage 1 Traffic Calming
? Step 5: Data Collection for Stage 1 Traffic Calming
? Step 6: Stage 2 Traffic Calming
? Step 7: Applicable Traffic Calming Measures
? Step 8: Community Notification
? Step 9: City Council Approval
? Step 10: Implementation and Analysis

The Engineering, Public Works, Police, and Fire Departments have gone through the MTCP review process and agree that speed lumps (stage 2 traffic calming measures) along Wawona Street and Elm Avenue are warranted. Contingent upon approval, Public Works staff will install the speed lumps. Attachment 1 shows the proposed locations of the speed lumps.

Fiscal Impact:
There is sufficient funding in the FY 2...