File #: 25-285    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 5/19/2025 In control: CITY COUNCIL
On agenda: 6/17/2025 Final action:
Title: Adopt a resolution amending the Fiscal Year 2024-25 Capital Improvement Program to include the Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project and assign a Capital Improvement Project Number; approving the Plans and Specifications for the Wawona Street Bike & Pedestrian Improvement Project; approving the California Environmental Quality Act (CEQA) Notice of Exemption determination (exempt from CEQA pursuant to 14 Cal. Code Regs. ? 15301(c), and the Project Claim for the Measure K Renewal Bicycle, Pedestrian, and Safe Route to School Non-Competitive Program Cycle 2; authorizing a Call for Bids; and authorizing the City Manager or Designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
Attachments: 1. Attachment 1 - Resolution, 2. Attachment 2 - Invitation to Bid, 3. Attachment 3 - Notice of Exemption, 4. Attachment 4 - Location Map, 5. Attachment 5 - Measure K non-competitive program Claim Form
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Agenda
Memo to:
Manteca City Council


From:
Kevin Jorgensen II, Director of Engineering/City Engineer


Prepared by:
Toshi Sessoms, Assistant Engineer, Donna Zapico, Assistant Engineer


Date:
June 17, 2025


Subject:
Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project

Recommendation:
title
Adopt a resolution amending the Fiscal Year 2024-25 Capital Improvement Program to include the Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project and assign a Capital Improvement Project Number; approving the Plans and Specifications for the Wawona Street Bike & Pedestrian Improvement Project; approving the California Environmental Quality Act (CEQA) Notice of Exemption determination (exempt from CEQA pursuant to 14 Cal. Code Regs. ? 15301(c), and the Project Claim for the Measure K Renewal Bicycle, Pedestrian, and Safe Route to School Non-Competitive Program Cycle 2; authorizing a Call for Bids; and authorizing the City Manager or Designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.

body
Background:
On February 27, 2025, the City was awarded $3,814,045 in Active Transportation Project Cycle 7 grant ("ATP Cycle 7") funding by SJCOG. $400,000 was allocated to the Wawona Street (Union Road to Main Street) Bike & Pedestrian Improvement Project ("Project"). The ATP Cycle 7 grant has a 20% match requirement.

To expedite the construction schedule and optimize use of local funds, staff has prepared the Plans, Specifications, and Estimate ("PS&E") for the Project. The Project includes the addition of new class III bike lanes, placement of new asphalt concrete overlay, rubberized cape seal, pavement fabric, dig-out repairs, installation of ADA curb ramps, crack sealing, and striping.

The Project is located along Wawona Street from Union Road to Main Street (see Attachment 4 - Location Map) and may also include Locust Avenue from Wawona Street to Miss...

Click here for full text