City Council Agenda
Memo to:
Manteca City Council
From:
Kevin Jorgensen II, Director of Engineering/City Engineer
Prepared by:
Elba Mijango, Associate Engineer; Somporn Boonsalat, Deputy Director of Engineering
Date:
July 30, 2025
Subject:
Nile Garden Well 30 Water Supply Project (CIP 21026 & 21034)
Recommendation:
title
Adopt a resolution approving Amendment No. 2 for construction management and inspection services with Brown & Caldwell in the amount of $150,000 for the Nile Garden Well 30 Water Supply Project; and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
The City of Manteca ("City") and the Manteca Unified School District ("MUSD") partnered to secure a grant of approximately $8.37 million from the State Water Resources Control Board ("State Water Board") for the construction of Well 30 and all associated equipment necessary to supply drinking water to Nile Garden Elementary School. This effort is part of the Nile Garden Well 30 Water Supply Project, CIP 21026 and 21034 ("Project").
On June 20, 2023, the City Council awarded the Phase 1 construction contract to Nor-Cal Pump & Well Drilling ("Nor-Cal Pump") in the amount of $927,853 and approved an agreement with Brown & Caldwell ("B&C") for Phase 1 construction management and inspection services ("CMIS") in the amount of $206,867, see Attachment 5.
On March 5, 2024, the City Council awarded the construction contract for Phase 2 of the Project to T&S Construction in the amount of $4,925,000 and approved Amendment No. 1 for CMIS with B&C in the amount of $674,044, see Attachment 4.
In March 2024, during drilling activities at Well 30, the surrounding soil began to cave in. Drilling was paused, the area was stabilized, and a geotechnical investigation was conducted. The resulting report included recommendations that led to design modifications, including changes to the building an...
Click here for full text