City Council Agenda
Memo to:
Manteca City Council
From:
Michael Selling, Assistant Director of Engineering/City Engineer
Prepared by:
Donna Zapico, Assistant Engineer;
Toshiro Sessoms, Assistant Engineer;
Somporn Boonsalat, Deputy Director of Engineering
Date:
March 17, 2026
Subject:
Notice of Completion for the Wawona Street Bike & Pedestrian Improvement Project CIP 25019 (Wawona Street: Union Road to Main Street and Locust Avenue: Wawona Street to Mission Ridge Drive)
Recommendation:
title
Adopt a resolution accepting all improvements for the Wawona Street Bike & Pedestrian Improvement Project CIP 25019 (Wawona Street: Union Road to Main Street and Locust Avenue: Wawona Street to Mission Ridge Drive) as complete; authorizing the City Clerk to file the Notice of Completion; and authorizing the City Manager or designee to complete and execute all associated documents, and take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
On July 30, 2025, the Manteca City Council awarded the construction contract C2025-151 for the Wawona Street Bike & Pedestrian Improvement Project CIP 25019 ("Project") to George Reed, Inc. ("Contractor") in the amount of $1,516,123.10 and approved a construction contingency of $58,474.58 for a total not-to-exceed Project cost of $1,574,597.68.
On December 16, 2025, City Council approved an additional $30,000 in Project contingency for a total Project contingency of $88,474.58 for a revised not-to-exceed total Project cost of $1,604,597.68.
The Project was constructed in general conformance with the conformed plans and specifications.
The Project included one change order totaling $80,672.44.
The change order work included the following:
* Additional 2" grind and overlay for Locust Avenue
* Balancing change order to reflect actual quantities installed
The final construction cost is $1,596,795.54 and the Contractor has signed the final paym...
Click here for full text