Accept Grant of City Utility Easement from Brocchini Family Partnership for the Central Sewer Trunk Project CIP 24004 |
Recommendation:
title
Adopt a resolution accepting a Grant of City Utility Easement from Brocchini Family Partnership, totaling 4,337 square feet located at 1595 W Yosemite Avenue (APN 200-150-33), for the Central Sewer Trunk Project CIP 24004; and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.
body
Background:
In March of 2024, the City of Manteca (“City”) adopted the 2024 Wastewater Master Plan (“WWMP”). The WWMP identified the Central Trunk Sewer Project CIP 24004 (“Project”), labeled as Wastewater Collection System Project 06, as a high-priority project due to its location in the collection system, pipeline age, and risk of failure.
The Project will replace approximately 4,200 linear feet of existing 36-inch sewer line, with a new deeper 36-inch sewer line and abandon the existing Union Road lift station.
The new sewer line will connect to the existing 36-inch sewer installed as part of the 320 Airport Way Development and follow the future Center Street alignment east through the Kaiser Foundation Hospital property, then north and continuing east fronting the Brocchini Family Partnership properties.
Fiscal Impact:
There is no fiscal impact associated with this action.